Acquisition Timeline

Key Dates of the Preliminary Acquisition Timeline

PIN publication

19 January 2016
Open Market Consultation30 March 2016
Issue of the Contract Notice04 June 2016
Issue Request for Tenders10 June 2016
Deadline for submitting questions about tender documents30 June 2016 at 14:00
Bidders conference07 July 2016
Deadline for submission of Tenders for Phase 1 and the Framework Agreement18 August 2016 at 12:00
Opening of the tenders for Phase 122 August 2016

Tenders are notified of decision of the award of contracts

Start of the standstill period (min. 10 calendar days)

14 October 2016
Start of implementation Phase 13 November 2016
Completion Phase 112 May 2017
Issue Request for Tender for Phase 212 May 2017
Deadline for submitting questions about tender documents29 May 2017
Deadline for submission of Tenders for Phase 21 June 2017
Opening of the tenders for Phase 21 June 2017
Award Decision Phase 23 July 2017
Start of Implementation Phase 24 July 2017
Deadline for submission of Phase 2 final milestone(s)/End of Phase Report with deliverable(s) & End of Phase Review meeting1 August 2018
Results of Phase 23 September 2018
Issue Request for Tender for Phase 35 September 2018
Deadline for submission of Tenders for Phase 326 September 2018
Award Decision Phase 35 November 2018
Start of Implementation Phase 37 November 2018
Completion Phase 330 June 2021